SYSTEMS & NETWORK STATUS PAGE


17th May 2023

USDC ZAV Planned Maintenance - High & low voltage switchgear

Maintenance started at 08h00: Our supplier will be conducting maintenance on our high voltage switchgear, transformer & low voltage cables and switchgear.

We will perform a controlled switchover to backup power (generators) before our supplier starts the maintenance work and we will run on backup power for the entire duration of the maintenance. We don't expect any impact towards the power delivery of critical IT load. Our UPSes will provide backup power during the swap between mains and backup.

This maintenance has been logged with ticket ref. 00006439