Dear customers, we would like to inform you about the end of our maintenance of the high voltage upgrade.
We were able to finish the maintenance a day sooner than expected.
We switched the power supply of the datacenter back to the main grid connection.
We ran 58,50 hours on backup power. Everything worked as expected.
Due to our redundant power infrastructure we were able to perform this upgrade and have no impact to our customers critical IT load.
I would like to thank our suppliers Welec, Fluvius and OCB for their great work.